Home / Projects / 01 Moorebank Rooftop Array

Project 01 · Solar PV

Moorebank Rooftop Array

A strong daytime load sat beneath an underused roof, and an ageing switchboard made a single large connection the wrong first move. The array was delivered in two stages.

This account is an illustrative example of the company's method. Client names and commercial figures are not published; findings are qualitative and drawn from the records described below.

The brief

The building had one industrial occupant, a broad clear roof and a daytime load that rose soon after opening and fell before dusk. The main switchboard had been in service for many years: spare ways were scarce and its remaining capacity for an additional feed had not been established.

The owner wanted generation but did not want to replace the switchboard on speculation. A single-stage design would have passed the full array output through one connection point, requiring a board proven capable of carrying it. The office was asked whether the roof could be used without committing to a board replacement before any operating evidence existed.

That instruction governed the review. Options requiring a replacement board up front were set aside. Options placing a smaller, measurable load on the existing arrangement, with the larger decision deferred, were retained.

Site inputs

The engineers sized the array from interval data rather than annual consumption. The half-hour record was aligned with the operating day: demand rose shortly after the site opened, held a steady plateau through the middle of the day and declined in the late afternoon. On that profile, a substantial share of daytime generation would be consumed behind the meter rather than exported.

The roof survey separated usable area from apparent area. Parapet setbacks removed a strip around the edge, rooftop plant occupied pockets that appeared clear on the drawings, and a membrane nearing the end of its warranty life ruled out fixings that penetrate the waterproofing. The remaining zones were each recorded with the reason for inclusion or exclusion.

Site input sheet
Moorebank rooftop array

Load character
Daytime-weighted, with a steady midday plateau and a modest evening tail.
Roof condition
Wide clear areas, with parapet constraints, rooftop plant and a membrane that had to remain intact.
Mounting
Ballasted frames with no penetrations through the waterproofing layer.
Switchboard
Ageing assembly with limited spare ways; replacement not assumed in the first stage.
Connection
AC connection behind the existing metering, through a dedicated protection point.
Staging
Two defined stages; the second released only after a measured review of the first.
Verification
Generation, grid import and site demand read from one interval source.
Thermal record
Thermographic scan repeated after energisation, not only before it.

The governing constraint

A thermographic scan found no immediate fault at the switchboard. The engineers recorded the age of the assembly, the number of usable ways, the condition of terminations and the ratings of incoming and outgoing devices. A second scan during a busier period recorded how temperatures rose under load.

Available fault level was checked against the proposed protection settings. Generation could connect behind the existing metering without disturbing it, provided the new path had its own isolator and protection point. The conclusion was narrow: nothing demanded immediate replacement, and nothing justified assuming generous spare capacity. A single large array would have required one of those two claims; the staged option required neither.

The two paths were compared by their commitments. The single-stage design moved a major capital decision forward and concentrated the whole output at one connection point. The staged design put a smaller load through that point, measured it, and deferred the larger decision until measurement existed. The owner chose the staged path.

Ballasted frames across the clear roof zone; cable routes sized for both stages at first installation.
Dedicated isolator and protection point added at the existing switchboard; the assembly itself was not replaced.

Response: two stages with a release gate

Each stage was designed as a complete installation. The first had its own protection settings, isolation point and protection device, and did not depend on future work to be safe or to be signed off. The second was planned in detail but not committed. Cable routes and protection devices were sized for the finished arrangement from the outset, so a small amount of inactive infrastructure was installed early to avoid a second round of roof work later.

Energised equipment was labelled separately from equipment installed in advance. The first stage was handed over as a complete installation; the second remained a prepared option with its release conditions written down.

The installation crew set ballasted frames across the clear zones without penetrating the membrane. Setbacks were kept from parapets and rooftop plant. Areas affected by the work were documented at handover so later maintenance decisions would not need to reconstruct what had been disturbed.

Technical issues resolved

The switchboard was addressed by limiting the first stage to what the existing arrangement could accept. A dedicated isolator and protection point were specified, settings were checked against the existing arrangement, and the thermographic survey was repeated after energisation so the condition of the board under generation was recorded.

The membrane was addressed by the mounting choice. Ballasted frames avoided penetrations and the associated warranty question. Where earlier repairs had changed the surface, the engineers recorded how water sat after rain, because ballasted frames distribute load differently over a patched area. Several locations were left empty rather than forced into the layout.

Monitoring rules were agreed before commissioning. Generation output, grid import and site demand were read from the same interval source. Ambient conditions were logged and changes to the operating pattern were noted, so the comparison rested on like-for-like records.

Staged delivery

Stage one energised as a complete installation; stage two held as a documented option with written release conditions.

Verified against interval data

Generation, grid import and site demand read from one interval source across a full operating cycle.

No production interruption

Connection and roof work completed without interrupting the site's daytime operations.

Outcome and handover

The first stage operated inside the existing switchboard envelope and contributed to daytime demand. The review confirmed generation was being consumed on site at the times the load profile predicted. The second stage remained a decision rather than a commitment, with its release conditions recorded before the first frame was set.

At handover the owner received the survey zones, the thermographic records, the protection settings, the cable route drawings and a statement of which parts of the roof had been disturbed. Exclusions were documented alongside inclusions, and the second stage was recorded with its own conditions.

Questions about this project

Why was the array split into two stages instead of one?

The switchboard's remaining capacity had not been established, and the owner would not replace it before operating evidence existed. A single-stage array would have concentrated the full output at one connection point on an ageing assembly. The staged design capped the first connection at what the existing arrangement could accept, measured its behaviour under load, and made the second stage conditional on that record.

How was the array size determined from the load data?

The engineers used half-hour interval demand aligned with the operating day, not annual consumption. The profile showed a morning rise, a midday plateau and a late-afternoon decline, indicating most daytime generation would be self-consumed. The first-stage size was then bounded by the switchboard's demonstrated capacity, with roof zones excluded for parapet setbacks, rooftop plant and membrane condition.

Why were ballasted frames used rather than penetrated fixings?

The roof membrane was nearing the end of its warranty life, and any penetration would have raised a warranty question ahead of the generation question. Ballasted frames transfer load without breaching the waterproofing. Over previously repaired areas, ponding behaviour after rain was recorded before frames were placed, and some locations were left empty where the surface could not take the distributed load.

How was performance verified after energisation?

Generation output, grid import and site demand were read from a single interval source under monitoring rules agreed before commissioning. Ambient conditions and changes to the operating pattern were logged. Thermographic scans of the switchboard were taken before and after energisation, and protection settings were documented at the point of connection.

Why was the array staged rather than built at once?

The switchboard could not accept the full connection, and no measured performance existed for the roof zone. The first stage produced both: a dedicated protection point and a season of output data. The second stage was sized against that data rather than a forecast.

What did the roof require before ballasting?

A structural check, the membrane warranty terms and a layout that kept maintenance routes clear. The fixing method was agreed with the membrane supplier's conditions, and cable routes were planned for both stages at the outset so the second did not reopen the roof.

How was the second stage authorised?

Against measured output, the completed board work and an updated demand profile. The scope recorded the gate before stage one began, so the decision was made on evidence rather than on momentum.

Client comment

On the second stage.

A comment on what the measured data changed.

“

The second stage was decided on the first stage's output, not on a spreadsheet. That is why we were comfortable releasing the capital.