Home / Projects / 04 Warehouse Solar & Storage

Project 04 · Solar and storage

Warehouse Solar & Storage

A large roof, a modest daytime load and a constrained export connection made a smaller installation the better answer.

This account is an illustrative example of the company's method. Client names and commercial figures are not published; findings are qualitative and drawn from the measured record.

The site and the two limits

The building was a large distribution warehouse with an expansive, mostly unobstructed roof. A first sketch had filled that roof with panels. The site data did not support it: ambient load was modest and fairly flat through daylight hours, and the network connection carried an export limit that would be reached well before the roof was full.

The export condition had not appeared in the first set of documents. It emerged when the connection agreement and the network details attached to the metering were requested. The permission allowed only a modest flow back to the distribution network at the times when generation would be highest.

The operator also raised a future question: possible electrification of material handling equipment, with no committed date and no defined load. Building for that uncertainty would have meant installing generation that could not be used under the present connection conditions. The engineers were asked to test whether a smaller array with a companion battery could serve the site as it was while leaving room for a later load.

Option A

Fill the available roof

A roof-sized array reaches the export ceiling early in the day and spends much of the afternoon curtailed.

  • Output beyond the connection limit cannot be exported or consumed.
  • Additional panels add cost without adding usable generation.
  • Roof zones reserved for a future load disappear under the layout.
Option B — adopted

Size to the usable envelope

The array was set by the smaller of two limits: what the site could consume at midday and what the network would allow back. The remaining roof was left clear deliberately.

  • Generation stays inside the known export condition.
  • A companion battery absorbs surplus that would otherwise be curtailed.
  • Clear zones and cable routes remain available for a later load.
RoofLarge and mostly clear, with area far exceeding what the present load could absorb.
Ambient loadModest and steady through daylight hours, rising slightly in the evening.
Export conditionConstrained at the distribution connection during the middle of the day.
Array sizingSet by the load and export envelope, not by the available roof area.
StorageA small battery paired with the array to absorb surplus and release it later.
Future loadUncommitted; clear roof zones and cabling routes left available for a later review.
VerificationGeneration, demand and export read from one interval source; battery flows logged separately.

Sizing method

The engineers compared the site's own demand at each interval with the export ceiling and identified the largest array that stayed inside both. That figure was well below what the roof could hold. It was tested against a full week of data and then against a week with different operating hours, rather than one representative day.

Despatch activity peaked in the morning and early afternoon, when a roof of that size would be producing hardest. The site's own demand rose with that activity but not enough to absorb a full array. Beyond a certain panel count, additional midday output would either be curtailed or pushed towards a connection already at its permitted flow. The design worked backwards from the limit instead.

The export condition was not treated as a single fixed number. The connection agreement described conditions applying at particular times, and the review read those conditions against the operating weeks. Two weeks with different despatch hours were used to test the proposed size. Where the record was incomplete, the gap was recorded rather than filled with an assumption.

Installed array zone; the remaining roof area left uncommitted and marked on the cable route drawing.
Storage cabinet set close to the distribution board, sized to absorb midday surplus only.

Connection conditions and reserved zones

Connection conditions sit with the network, not with the office. The design was written to the limit known at the time of the review, and that assumption was recorded in the scope. A future change to the connection is a separate question with its own assessment.

The reserved roof zones were kept clear and the reasoning documented. Cable routes were placed so the reserved areas retained a known path to the board. Ballasted frames can be adjusted or removed without leaving penetrations in the membrane, and the clear zones were marked on the same drawing as the cable routes, so a later decision about electrified equipment starts from a known footprint.

Storage duty

Storage was scoped to a narrow job: absorb surplus that would otherwise be curtailed, then release it into the evening rise. It was not sized to cover the site's evening demand, nor to support equipment that had not been specified. A larger battery would have spent long periods idle and required more switchboard space for no defined purpose. Keeping it modest also kept the connection work inside the envelope established for the array.

The duty cycle differed from a refrigerated site. A cold store has a steady overnight base punctuated by sharp compressor events, so a battery there is judged on response speed. This warehouse had a modest, fairly flat daytime demand and a gentle rise towards the end of despatch, with no comparable event to catch. The battery was configured for energy shifting, not event response.

Lease arrangement

The building was occupied under a lease, so the decision involved two parties. The operator wanted a system suited to current operations; the building owner wanted the roof protected and options preserved for the next occupier. The array stayed within the zone agreed in writing, non-penetrating mounting was used, and the areas left clear were documented. Cable routes were placed so they could be isolated without disturbing the rest of the distribution board.

Verification and outcome

Before installation, the checking method was agreed. Generation, site demand and export were recorded from the same interval source, with battery charge and discharge logged separately. Like-for-like operating weeks were compared and changes to despatch hours noted. The review asked how much generation was consumed on site and whether export remained within the agreed condition.

A greater share of the generation was consumed on site, export stayed within the connection condition, and the battery shifted midday surplus into the evening period. The roof retained uncommitted capacity for a future load. The outcome was checked against the way the site operated, not inferred from the size of the installation.

Export condition held

Recorded export remained within the connection agreement across the compared operating weeks.

Verified against interval data

Generation, demand and export read from one source; battery flows logged separately.

Future capacity preserved

Roof zones and cable routes left clear and documented for an uncommitted later load.

Questions about this project

Why was the array smaller than the roof could hold?

Two limits governed the size: the site's own midday demand and the export ceiling in the connection agreement. The engineers found the largest array that stayed inside both at every interval, tested against two operating weeks with different despatch hours. Panels beyond that point would have produced output that could neither be consumed nor exported, so they were excluded from the design.

How was the export limit established?

From the connection agreement and the network details attached to the metering, requested during the review because the condition did not appear in the initial documents. The agreement described time-dependent conditions, which were read against the operating weeks rather than a single quiet day. The applicable limit was recorded as an assumption in the scope; any future change requires its own assessment with the network.

What does the battery do at this site?

One defined job: absorb midday surplus that would otherwise be curtailed, and release it into the evening rise in demand. It is not sized for full evening coverage or backup, and it is not configured for event response, because the warehouse load has no sharp peaks comparable to compressor restarts at a cold store. Charge and discharge are logged separately from generation and demand so its contribution can be checked.

How were the interests of the operator and the building owner reconciled?

The physical scope was agreed in writing by both parties. The array stayed within a defined roof zone, ballasted mounting avoided membrane penetrations, and the clear areas were documented on the cable route drawing. Routes were placed so the installation could be isolated without disturbing the rest of the distribution board, preserving the roof and the options for a future occupier.

Client comment

On the export figure.

A comment on what changed the design.

“

The export limit was the number that mattered. Everything else followed from it once it was written down.