Sizing the array against the load, not the roof

A commercial photovoltaic system is shaped by demand, roof condition and connection capacity in that order. The technical questions that decide whether, and how, an array is appropriate.

The available roof area sets an upper limit on what could physically be installed. It does not, on its own, justify an array. Sizing starts with interval demand data: how much electricity the site uses and when it uses it. The result is then tested against the roof, the switchboard and the connection. Where those tests fail, the array is reduced or staged.

Site inputs
Required before sizing

Electricity data
Twelve months of bills and, where available, interval readings at half-hourly or finer resolution.
Tariff and demand charges
The current schedule and any charge that responds to short demand events.
Roof information
Plan, age, surface type, remaining warranty and any known repairs or previous penetration.
Structural detail
Existing drawings, or a reference to the party able to confirm load capacity.
Electrical information
Single-line diagram, switchboard condition and available space for protection and metering.
Connection terms
The network connection agreement and any limit on export.
Operating pattern
Occupied hours, shutdown periods and planned changes to the premises.
Tenancy and ownership
Who occupies the site, who owns the roof and how meters are arranged.
Site access
Paths to the roof, safe working areas and places where equipment can be isolated.

Why each input decides the design

Each item is requested because a different answer to it would produce a different array, a different sequence, or no array at all.

ConsiderationWhy it decides the design
Interval load dataShows the shape of demand across the day, not just an annual total. It sets how much generation the site can use at the moment it is produced and where a mismatch first appears.
Roof age and conditionThe array is expected to outlast a surface already near the end of its life. Remaining roof life is reviewed before a layout is committed; a planned replacement changes the sequence of work.
Orientation and pitchAspect changes the shape of the generation profile. A roof that produces strongly in the morning may match one site and miss another, depending on the load.
ShadingShade from plant, parapets, adjacent buildings or future development is considered as it changes output, not as a visual detail. Partial shade can influence how an array is divided into groups.
Penetrations and servicesExisting roof fittings, access points and services constrain where modules can sit and how maintenance will reach them later.
Structural checkLoad capacity is reviewed by the appropriate qualified parties. Structural adequacy is a condition of proceeding, not a matter to resolve after installation.
Roof warrantyWarranty conditions can restrict how the surface is penetrated or altered. The requirement is identified during review so it is not discovered at installation.
Switchboard capacityThe point of connection must accommodate the proposed system. Space, protection arrangements and condition are assessed before a size is settled.
Export limitsA network limit can make a larger array largely unusable at certain hours. The limit is a design input from the first sketch, not a late discovery.
TenancyA single-occupier site and a multi-tenancy building raise different questions about who benefits from generation and how common areas are metered.
RoofRemaining surface life and membrane warranty conditions are established before a module layout is committed.
InstallationLicensed electrical trades carry out the installation and testing; the scope names that responsibility.

From sizing to layout

Once a target size is established from the load, layout work begins. Modules are arranged to suit the usable roof, with shade, access paths and penetrations treated as fixed conditions. String grouping and inverter configuration follow from that layout: modules with different shade profiles may be grouped separately, and the choice between one larger inverter and several smaller units depends on how the array is divided and whether future expansion is planned.

Product selection, protection settings and final electrical design belong in a site-specific scope. The principle applied here is that the electrical arrangement follows the physical layout and the demand pattern, so the system behaves as intended across the day rather than only under ideal conditions.

Export constraints and metering

Export limits arrive in writing from the network. They are conditions of connection, not details negotiated after installation. If the network allows only a modest amount of generation to flow back, an array sized to fill the roof will spend part of its day curtailed. The limit enters the first sizing exercise, so the array is sized against what the site can use and what the connection can carry, whichever is smaller. The available responses are a smaller array, a change to the operating pattern so more generation is consumed on site, or staging with the second stage held until the connection or the demand is better understood.

Generation, site consumption and any export are read separately, because a single combined figure cannot show whether the array is serving the premises or passing energy to the network. The metering arrangement is designed at the same time as the array. After handover it allows a change in the site's demand to be seen in the same records that describe the system's output, so the original sizing decision can be tested against measured behaviour.

Roof conditionDesign responseWhat it changes
Sound surface with long remaining lifeStandard layout on the usable area, with access paths and penetrations set out before string grouping.Fewest sequencing constraints; the array can follow the planned programme.
Near end of surface lifeRoof renewal placed before installation, or the array staged until that work is complete.Prevents equipment being removed to replace the surface beneath it.
Partial shade from plant or parapetsUsable area reduced and affected modules grouped so shading does not drag down the rest of the array.Lower nameplate capacity, but output that better matches real conditions.
Heavy services or many penetrationsModule fields broken around fixed services and maintenance routes preserved.Layout becomes irregular, and access remains workable for the system's life.
Structural capacity uncertainA qualified assessment made a condition of proceeding; the array is not finalised until it is resolved.The project pauses at a gate instead of discovering the problem at installation.
Warranty restrictions on penetrationFixing method and penetration points agreed with the relevant parties before the layout is settled.Avoids a conflict between the array and the roof warranty.

The decision path for an array

The steps below describe how a photovoltaic scope is reached. Each ends with a decision that can be recorded, and any one of them can end the proposal before equipment is ordered.

01

Read the load

Interval demand establishes the size that would be useful. Annual totals alone cannot show whether generation lands when the site can absorb it, so a profile by time of day is the starting point.

02

Verify the roof

Structure, surface condition, remaining warranty and access are checked. A roof that needs work first puts that work into the sequence before any panel is fixed to it.

03

Confirm the connection

Switchboard capacity and the network export limit are obtained in writing. The smaller of useful demand and allowable export sets the practical ceiling on the array.

04

Settle the layout

Usable area, shade, services and maintenance routes determine where modules sit. String grouping and inverter arrangements follow from that layout rather than preceding it.

05

Choose a stage or a single step

Where demand or roof work will change, the array is divided into stages. A first stage provides operating evidence for the second while keeping the initial commitment aligned with what is known today.

06

Write the scope and commission

Assumptions, exclusions and responsibilities are recorded. At completion the installed layout, electrical tests, settings and metering separation are checked and handed over with the file.

Terms used in a solar scope

Self-consumption

The share of generation used by the premises at the moment it is produced. It depends on the match between the load profile and the generation profile, not on the nameplate capacity of the array.

Export limit

A condition of the network connection that caps the flow back to the grid. It is a design input from the outset and is not changed by selecting different equipment.

Curtailment

Generation deliberately not delivered because the site cannot use it and the connection cannot accept it. Curtailment expected at particular hours is stated in the sizing, not discovered after commissioning.

String grouping

The way modules are electrically grouped. Modules with different shade profiles are often separated so that one shaded section does not reduce the output of the whole array.

Staging

Dividing a project into steps, with a later step decided in the light of measured performance from the earlier one. Staging suits sites where demand, roof work or connection terms are still changing.

Metering separation

Reading generation, consumption and export as distinct quantities, so system behaviour can be verified after handover and compared with the sizing assumption.

Single occupier, multiple occupiers

On a single-occupier site, generation usually benefits the same entity that funds it and consumes the output. In a multi-tenancy building, electricity may be metered to several occupants while the roof belongs to a landlord or an owners corporation. That arrangement raises questions about who receives the benefit, how common areas are treated and how metering is configured. These are identified during review, and where the arrangements are not settled the design is held at a gate.

A roof may span tenancies with different operating hours, so generation occurs while some occupiers are absent. Common areas introduce an apportionment question, and an owners corporation may hold a view about penetration of the membrane that differs from an occupier's view about output. The scope records who funds the system, who receives the output and who maintains access.

Commissioning, metering and access

Commissioning tests the design against the site. Installation is checked, the system is brought into operation and the relevant tests and settings are recorded. Metering is configured so generation, consumption and any export can be read separately. Maintenance access is resolved at layout stage: safe access, equipment location and the ability to isolate components without disturbing other parts of the site are settled on the drawing.

The specific tests and settings belong in the site scope. The list below is the shape of the record a client receives.

  • Installation against the layout. Module position, fixing, cable routes and access paths are compared with the approved drawing, and any departure is recorded.
  • Electrical testing. Licensed electrical trades carry out the relevant tests and provide the documentation referenced in the handover file.
  • Metering separation. Generation, consumption and export are confirmed as separate readings, so behaviour can be checked after the file is handed over.
  • Protection and settings. Settings are recorded as installed, not left to be inferred from the equipment or from a default configuration.
  • Operating notes. The client receives a plain account of how to read the system, who to contact and what to do if output changes unexpectedly.
  • Outstanding items. Anything unresolved is listed with its status rather than left implicit at handover.

These records allow the original sizing decision to be checked. An array producing less than expected may be behaving as designed under a constraint identified at the start; the metering and the records distinguish that from a fault. The Moorebank office keeps them with the scope.

Scope of the work

Commercial solar PV is scoped site by site. A written scope states the array size, the mounting, the connection arrangement, the exclusions and the checks that remain outstanding, and it replaces any general description of the technology. No general statement sets out rebates, savings percentages or approval outcomes, and household systems are outside the company's scope. Structural, electrical and network checks are carried out for the site before work proceeds. For the surrounding sequence see How We Work; for the way solar fits alongside other measures see All Solutions.

Technical questions about commercial solar PV

How is roof suitability established?

Four things are checked before a layout is drawn: surface type and age with remaining membrane warranty, structural load capacity confirmed by qualified structural parties, orientation and pitch with shading from plant, parapets and adjacent buildings, and existing penetrations, services and access routes. A surface near the end of its life puts roof renewal ahead of installation, or the array is staged until that work is complete. Warranty conditions can restrict how the surface is penetrated, so the fixing method is agreed with the relevant parties before the layout is settled. Structural adequacy is a condition of proceeding.

How is the array sized against the load?

Interval demand data at half-hourly or finer resolution establishes how much generation the premises can absorb at the hours it is produced. That figure is compared with the usable roof area and the connection's export allowance; the smallest of the three sets the practical size. Annual consumption alone is not used, because two sites with the same total can have very different daytime profiles. Where demand is expected to change through an expansion or an efficiency measure, the array is staged so the second step is sized against measured behaviour.

What happens when the network imposes an export limit?

The written limit becomes a design input from the first sizing exercise. Generation above the limit at hours when the site cannot consume it is curtailed, so that output is not counted in the sizing. The responses considered are a smaller array matched to on-site use, shifting load into daylight hours so more generation is self-consumed, or staging with the second stage held until connection terms or demand change. Export conditions are administered by the network and cannot be altered by equipment selection.

What if the switchboard has no spare capacity?

The point of connection must accommodate the proposed system, so switchboard condition, available space for protection and metering, and the single-line diagram are reviewed before a size is settled. Where capacity is insufficient, the options are a board upgrade or replacement, a different point of connection, or a reduced array. That work is carried out by licensed electrical trades and is named in the scope with its own cost and programme implications. It is identified during review rather than discovered at installation.

Can an array be installed on a multi-tenancy building?

It can be assessed, but the commercial arrangement must be settled first. Electricity may be metered to several occupants while the roof belongs to a landlord or an owners corporation, so the scope records who funds the system, who receives the output, how common-area load is apportioned and who maintains roof access. Tenancies with different operating hours change which occupier benefits from generation at a given hour. Where those interests are not aligned, the design is held at a gate until the agreement is clear.

How is maintenance access handled?

Access paths, safe working areas and isolation points are set out on the layout before string grouping is fixed. Module fields are broken around fixed services so plant, roof hatches and drainage remain reachable, and inverters and combiner boards are positioned where they can be reached without moving stock or entering a restricted area. Components must be isolatable without disturbing unrelated parts of the site. These positions are recorded in the handover file together with the installed settings.

How is inverter capacity set against array capacity?

The ratio is chosen from the demand profile and the export limit. A modest oversize lifts output in diffuse light and shoulder hours at the cost of midday clipping; where export is capped, the ratio is set so that clipping falls in hours the site cannot use anyway.

What fixing method is used, and who warrants it?

Ballasted, mechanically fixed or hybrid, chosen against membrane type, wind region, structural certification and roof warranty. The method and the party responsible for each element are recorded before installation.

How is performance checked after commissioning?

Generation, consumption and export are metered separately, and the first months are compared with the modelled expectation adjusted for weather. A shortfall is then traced to soiling, shading, clipping or a fault rather than assumed.

Sizing

What decides the practical size of an array.

Three figures compete: what the roof can hold, what the site can use, and what the connection can accept.

A roof area establishes what could physically be installed, not what should be. Interval demand shows how much generation the premises can absorb in the hours it is produced; the connection agreement shows how much may be exported beyond that. The smallest of the three sets the practical size, and the written scope records which figure bound it.

Inverter capacity is then set against array capacity rather than matched to it. A deliberate oversize recovers output in diffuse light and shoulder hours, and accepts clipping at midday. Where export is capped, clipping is placed in hours the site cannot consume or export anyway, which turns a loss into a design choice.

Staging is used where one input is uncertain: a switchboard awaiting replacement, a load expected to change after an efficiency measure, or a connection enquiry still open. The first stage is sized to capacity that is already confirmed, and the second is sized against measured behaviour rather than forecast.

Client comment

On starting from the load.

A comment on why the array was sized from demand rather than roof area.

“

The array was sized to what we could use, not to what the roof could hold. That was the first time a proposal had started from our load.

Plant engineerManufacturing site, south-west Sydney

Discuss a site

Send the site suburb, the roof type and the question; the Moorebank office replies with the data needed to size an array.

This form prepares an email in your own mail application. Details are handled under our Privacy Policy.