This account is an illustrative example of the company's method. Client names and commercial figures are not published; findings are qualitative and rest on the measured record.
The site and the question
The distribution centre was lit by high-bay fittings across a large floor area. Despatch and picking kept the lighting on for long hours, often well beyond the core business day. The operator was not considering generation. The question was whether the existing installation could be changed in a way that could be demonstrated afterwards. Earlier conversations had produced claims that were difficult to check, because no baseline had been recorded and operating hours varied from week to week.
The measurement method was agreed at the outset, while the old fittings were still in service. The comparison had to be settled before any replacement and had to accommodate the fact that no two operating weeks were identical.
Inventory and baseline
Fittings, circuits, control zones and operating hours were recorded together. A luminaire count alone does not establish how long a fitting is energised. Some circuits shared distribution boards with other loads, so a whole-site meter comparison would have mixed the lighting effect with everything else on the site.
Temporary sub-metering was placed on the lighting circuits, and lux readings were taken at the work plane in each zone. One untreated zone was retained throughout the programme, so a change in activity could be separated from the effect of the replacement.
The installation was not uniform. Different areas used different fittings, and some zones had been extended over time with products that no longer matched their neighbours. Most circuits were switched as a group, so a zone that needed light for only part of a shift was lit for the whole of it. The engineers separated the question of the fitting from the question of the control: replacing lamps without addressing the switching pattern would leave the same hours of illumination.
The measurement plan specified how long the baseline would run and what would invalidate it. Operating hours were taken from the despatch roster rather than a single switching timetable. The condition of existing fittings and the presence of local controls were noted, because a fitting switched off for long periods is not equivalent to one energised all shift.
Programme sequence
Baseline and pilot
Lighting circuits were measured before any change, then one aisle was treated as a pilot. The engineers checked that the metering and the lux survey produced repeatable readings.
Fix the comparison method
Consumption was normalised for illuminated hours and checked against the untreated zone. The method, including excluded weeks, was written down before the rollout.
Replace aisle by aisle
Later aisles were changed outside peak despatch, with the sequence agreed with the operator so picking routes stayed open. The untreated zone remained intact as the reference.
Re-measure at the work plane
Lux was checked at the same points and under the same conditions as the baseline, zone by zone, before the next aisle was released.
Report method with result
The operator received the baseline, the comparison rules and the post-install readings together, so the result could be examined rather than simply accepted.
Why circuit-level metering
The sub-metering was installed on the lighting circuits rather than at the main intake because several of those circuits shared boards with other loads. Isolating the lighting at circuit level made the comparison narrower: a change in despatch activity would show up in the reference zone, where it could be recognised, rather than being attributed to the new equipment.
Comparing weeks with different operating hours was handled by normalising consumption for the hours the lighting was actually on and keeping the untreated zone as a reference. A busier week could then be distinguished from a change caused by the new fittings. The method was reported alongside the result, with the excluded weeks and the counting rules set out.
Because one zone was left untouched for the whole programme, any shift in the reference reading could be investigated before the next aisle was signed off. A week of unusual despatch activity could be set against the reference and understood rather than discarded on suspicion.
Lux requirements
Lux readings were taken at defined points on the work plane and repeated under matching conditions after each stage. The objective was maintaining the level the tasks required, not maximising the reading at the sensor. Where a zone had been over-lit under the old arrangement, the inventory recorded that fact, and the replacement was judged against the task requirement rather than the original reading. A lower lighting load counted as a good outcome only where the work plane remained adequate.
Operating changes identified by the inventory
Once the lighting was measured, two operating changes followed. Zones with irregular use were given local switching so they no longer came on with the whole circuit, and the cleaning schedule was moved to periods when daylight contributed more to the work plane. Neither change required new plant. Both were recorded separately from the replacement so the operator could see which part of the result came from equipment and which from behaviour.
Scope boundary and sequencing
No switchboard work and no generation were folded into the lighting scope, which kept the measured boundary clean. The installation crew worked in occupied areas and kept the untreated zone intact throughout, because that zone was part of the comparison.
The efficiency work was sequenced before any future generation review. Part of the site's evening demand was created by lighting that stayed on longer than the task required; reducing that demand first makes a later generation question smaller and clearer, and avoids sizing panels against a baseline the operator would soon change.
Outcome
The lighting load was lower under the agreed comparison method, while measured lux at the work plane was maintained across the treated zones. Because no generation was added, the change was attributable to the lighting work alone. The operator received the baseline, the method, the zone records and the post-install readings together.
Lighting circuits sub-metered and normalised for illuminated hours against the retained reference zone.
Measured at the same points before and after, across the treated zones, under matching conditions.
Aisles replaced outside peak despatch with picking routes kept open; no generation or board work in scope.
Questions about this project
Why was the measurement method fixed before any fitting was replaced?
Operating hours varied from week to week, and earlier claims at the site had been impossible to check because no baseline existed. Fixing the method first — baseline duration, normalisation for illuminated hours, exclusion rules and the retained reference zone — meant the post-installation comparison could be reproduced by the operator rather than accepted on trust.
Why sub-meter the lighting circuits instead of using the main intake meter?
Several lighting circuits shared distribution boards with other loads. A whole-site reading would have mixed the effect of the fittings with the effect of everything else on the site. Circuit-level metering isolated the lighting load, and the untreated reference zone made changes in despatch activity visible so they were not attributed to the new equipment.
How were weeks with different operating hours compared?
Consumption was normalised for the hours the lighting was actually energised, taken from the despatch roster rather than a switching timetable. The untreated zone provided a live reference: a busier week showed up there first and could be distinguished from a change caused by the replacement. Excluded weeks and counting rules were written into the method before the rollout.
What role did the pilot aisle and the untreated zone play?
The pilot aisle tested both the fitting and the repeatability of the metering and lux survey before the wider rollout, so a flaw in the comparison would be found early. The untreated zone stayed in service for the whole programme as the reference for activity changes; it was not removed after the pilot. Each subsequent aisle was released only after its work-plane lux was re-measured at the baseline points under matching conditions.
How was the lighting baseline established?
From circuit-level sub-metering and a lux survey, with operating hours recorded rather than assumed. The baseline covered a representative period before replacement and included the weeks that would later be excluded from comparison.
Why sub-meter the lighting circuits?
Several circuits shared boards with other loads, so a whole-site reading would have mixed the fittings' effect with everything else. Isolating lighting at circuit level made the comparison narrower and defensible.
How were weeks with different activity normalised?
For the hours the lighting was actually on, using the untreated zone as a reference. A busier week could then be distinguished from a change caused by the new fittings rather than being read as savings.
Related work
Advisory review and staged array.
Two accounts where sequence and evidence mattered.
Client comment
On agreeing the method first.
A comment on measurement and verification.
“Agreeing how the result would be measured before we started removed the argument about whether it worked.